Development · 5 to 30 unit schemes in Bali and Lombok
The pre-PBG owner's checklist.
The building approval is the last moment the owner holds every card: land, design, contractor, rate and terms. After it the contractor holds the programme, and every unchecked claim is a decision made for you.
The checklist
Every card you hold, with the number or the conflict behind it.
The site and the permit
Perda 2/2023 · pink tourism, yellow residential, green protected · rooms need the tourism colour
Insurers refuse structures inside the line; 48 structures came down at Bingin in July 2025.
Conflict: 15 to 30 m in one guide, 50 to 100 m in another. Plan on the wider figure until the geotechnical report and Badung PUPR fix it.
It fixes the buildable line, and the PBG file and the insurer both want it.
15 m island-wide, enforced on the Bukit
A directive, not a regulation, and the sources disagree.
Conflict: 2026 guidance covers Tabanan, Jembrana, Buleleng, Bangli, Karangasem and Klungkung and exempts Badung, Gianyar and Denpasar; 2024 to 2025 reporting described a Sarbagita version; no Pergub codifies either. Verify at DPMPTSP Badung.
Parts of the Bukit have no mains water; 10,000 to 20,000 litres of storage is the working norm
Fitness centre 93116 in our notes, marked verify · Permenpar 6/2025 raises the bar from 2026
KKPR through OSS, then PBG, then SLF · PBG quoted at 6 to 10 weeks in Badung on a complete file; we have watched it take a year
The numbers
Every figure moves when an input changes; a slide cannot.
On our sample model the rate alone moves profit on cost from 51% to 22%, sales unchanged.
IDR 10m to 16.5m per m² · sales hold at $7.6m · profit $2.1m to $1.2m · change the rate in the sample model
IDR 8 to 12m per m² entry · 12 to 18m mid · 18 to 20m+ design standard · pool, landscape and fit-out usually extra
Pecatu leasehold IDR 19.5m to 35m per are a year · prime ocean-view freehold asks to IDR 1.15bn per are
Build cost, sales pace, rate and occupancy, one at a time.
Ramp to maturity usually 12 to 24 months
The contract
The contractor who bills against it should not have written it.
An unchecked claim is a decision made by the contractor.
A payment falls due on a dated photo, a location and a named sign-off.
Reg 11/PRT/M/2019 mandates milestones but requires no escrow and no independent verifier
The final payment is your only hold over the snag list.
A decision while ahead of you; history once the wall is up.
The documents
"Which revision is current" must have one answer.
WhatsApp photos are the Bali norm; a thread is not a record.
A change nobody signed is a change nobody owns.
The sales and the opening
Different cash flows, and off-plan sales carry their own rules.
A PPJB needs 20% construction completion (Reg 11/2019) · deposits sit in the developer's account, so verified milestones are also your sales proof
Lender pack and buyer page must trace to one set of numbers.
Bali brochures routinely claim 20 to 25%; the market-norm gross villa yield is 6 to 10%
A property that opens invisible pays OTA commission for its own demand.
A real property named in 6% of valid assistant answers, none by ChatGPT · 76% OTA share at a live property · the baseline is free
Figures are from public Bali guides and listings checked 5 September 2026 and from our own engagements: a practitioner's map, not legal advice. The answers for your plot come from DPMPTSP and PUPR in your regency, in writing.
What we do at this stage
The model before the money, the controls before the first claim.
The Development Feasibility & Financial Model builds groups 02 and 05 from your quantities and quotes, with the first working version within days of the documents arriving. The Development Control System starts with a two-week look at how the project actually runs and puts groups 03 and 04 into accounts you own before the first claim lands. Both come from a project we once ran by hand, and would not run that way again.